Apply for point of discharge

Stormwater must be connected to a legally approved point of discharge. A point of discharge is usually an underground drain, kerbs or open table drains.

Online

Step 1.Apply

Complete the details, including property address and the works your completing

Step 2.Pay

Pay the $157.00 fee to complete your application

Step 3.Assessment

Please allow 10 business days for us to process your application. The construction of an outfall drain to the nearest Council asset may be required.

Apply for a stormwater point of discharge certificate

Step 1

Stormwater must be connected to a legally approved point of discharge. A point of discharge is usually an underground drain, kerbs or open table drains.

To meet our stormwater drainage requirements for a planning or building permit, please follow these steps:

Apply for a stormwater point of discharge certificate

  • Please allow 10 working days for us to assess this application.

  • The construction of an outfall drain to the nearest Council asset may be required.

  • Fee $65.40.

 

Step 2

Submit your stormwater drainage plans and computations

  • Refer to your planning permit for your stormwater drainage requirements.

  • Please allow 20 working days for us to assess this application.

  • Fee varies from $175 to $1000.

 

Step 3

Apply for a works within a road reserve permit

  • A works within a road reserve permit is required to install any new stormwater connection.

  • Please allow 10 working days for us to assess this application.

  • Fee $240.50. Security bond (where applicable) $1000.