Morris Road Work Site
Despite more than 25 days of rain, local flooding, and strong wind conditions since we started this project, our construction crews have been working hard to keep the works moving forward.
Since the last update we have completed the sub-surface tree vaults, constructed the curb and channel, poured the concrete slabs for the spaces, poured the concrete plinths for the seats, laid the Bluestone Pavers, and re-laid the footpaths to match the new Sit, Meet and Eat spaces.
The remaining works planned for the next couple of weeks (weather permitting) include sealing the stone pavers and seat plinths, reinstating the road surface near the curb and channel, fitting the new seats and planting our magnificent hand selected Golden Rain Trees and understory plants.

(Left to Right: Tree Root Vault, Concrete Slabs & Curbs, Plinths Forms, Paving & Seat Plinths, New Footpaths)
Morris Road Work Site
Works started in Main Street outside the Fat Goat last week with the initial excavation, drainage connections and set-out the sub-surface tree vault system.
The works will pick up pace here over the next few weeks with the sub-surface tree vaults finished, the concrete slab and seat plinths formed and then poured, the ramp and stairs constructed and the same Bluestone pavers as the Main Street laid.
Once this is completed reinstatement works on the road and footpath, fitting of handrails, seats and then planting of our two new Golden Rain Trees and understory plants will see this site ready for the community to use.

(Left to Right: Starting at Morris Rod & Sub-surface Tree Vault System)